03 Apr Mounting Tech Steps: Non-Penetrating Mounts
Mounting Tools
- Stud finder
- Marking tool
- Drill
- 7/32” drill bit
- Level
- 1/2” nut setter
- 1/2” socket wrench
- 7/16” wrench
Notes
- Key steps bolded
- All lags must be tightened snug plus a 1/4 turn
Rail
Supplies
- Mount
- Hardware
Process
- Determine proper location for rail mount on railing
- Recommended location: where vertical rails intersect with either bottom or top horizontal rail
- Never affix rail mount on railing that is rusted, bent, or cracked, has deficient or broken welds/connections to top or bottom horizontal rails, or is not structurally stable in connection to building
- Place plate #1 on top of plate #2
- Place first external tooth lock washer and then flat washer onto the 1/4″ x 20 x 1 1/2″ bolt
- Then insert bolt/lock washer/flat washer assembly through slot in plate #1 and thread into plate #2
- Set assembled plates at install location on railing
- Adjust two plates so as to lightly clamp opposing edges of plate assembly to vertical rails and then tighten securely four 1/4″ x 20 x 1 1/2″ bolts
- Align plate #3 with plate #1/#2 on other side of railing
- Ensure part label for part #3 identifying UP is in proper direction
- Insert slots of plate #3 onto 1/4″ x 20 bolts from plate #1/#2 assembly
- Level plate #3 and secure mount to railing by threading onto 1/4″ x 20 x 1 1/2″ bolts, provided 1/4″ x 20 serrated hex nut
- Securely tighten hardware on assembly and ensure both rail mount and railing are structurally sound
- Seat mounting foot (not included) onto plate #3 using the 1/4″ x 20 x 1/2″ bolts with the external tooth lock washer and securely tighten
Non-Pen
Supplies
- Mount
- Hardware
- Mat
- Bricks
Assembly Process
- Take out mount
- Attach mast/footplate to mount
- Take out appropriate number of blocks
Installation Process
- Locate suitable location
- Transport mount and bricks
- Place mat on mounting location
- Place mount on mat
- Place bricks on mount
- Level mast and tighten hardware with 7/16” wrench
- Place dish on mast
VERSATILE
Supplies
- Mount
- Hardware
Installation Process
- Lift the tile in the row above
- Slide the support tongue onto the tile
- Lower the tile
- Repeat with other support tongue
- Place the base in selected location
- Lift the tile in the row below
- Slide hooks under the tile
- Place stiffener bar on top of the tongue
- Insert the hardware
- Attach the footplate
- Level mast and tighten hardware with 7/16” wrench
- Place dish on mast
Patio
Supplies
- Mount
- Mat
- Bricks
Assembly Process
- Take out mount
- Take out appropriate number of blocks
- Assemble the mount base
Installation Process
- Locate suitable location
- Transport mount and bricks
- Place mat on mounting location
- Place mount on mat
- Attach mast/footplate to mount
- Place bricks on mount
- Level mast and tighten hardware with 7/16” wrench
- Place dish on mast